Foundation work

Post Road Project

On our custom home on Post Road, we have finished foundation work including the basement slab. We will finish back filling the walls and begin framing next week!

image

image

Posted from WordPress for Android

Pouring Walls!

We poured foundation walls on our Post Road job today!

image

image

image

image

Posted from WordPress for Android

Foundation walls on Belle Park home

We are setting forms for our poured foundation walls on a new home in Belle Park. On most all of our homes, we pour solid walls as opposed to block walls. These walls are superior to block walls and increase the quality of our conditioned crawl spaces.

image

image

Posted from WordPress for Android

Nashville Project photos…

Here are some photos of one of our Belle Park homes currently under construction…

Framing is well underway and they are setting rafters on the roof this week.
Swimming pool has been formed and the shell has been poured.

image

image

image

Posted from WordPress for Android

Construction started in Belle Park

Kingdom Builders is excited to announce construction on a custom home in Belle Park!

Footings and walls have been poured and we will begin framing next week. Stay tuned for more photos and updates!

 

image

 

image

 

image

IMG_2534.JPG

Foundation work on Hwy 100 project in Nashville

We have finished our poured concrete walls and block work and are now pouring slabs for the new additions to this home in Nashville.

Framing scheduled to begin Monday!

20140110-222723.jpg

20140110-222730.jpg

20140110-222735.jpg